date锛?022-01-21
several days ago, the first core process module of the world鈥檚 first integrated constructed lng plant constructed by china successfully sailed out of the wharf of cooec qingdao yard. as planned, this module will be transported over a distance of about 5,170 nautical miles and delivered to the project site by the end of february for onsite installation.
the module consists of three decks with a total height exceeding that of a 13-storey building. during loadout, cooec used its independently designed spmt loadout technique and completed all spmt operations, directions, and other major tasks independently, marking cooes鈥檚 complete mastery of the core technology for the loadout of large lng plant modules using spmt and providing valuable experience for the subsequent loadout operations of other modules.
other than module a5ea delivered this time, the remaining modules are being constructed as planned. the overall construction progress is close to 65%.
during the execution of this project, the integrated construction of core process module and pipe gallery module was achieved for the first time in the world and many new methods and techniques were developed, signifying that cooec鈥檚 capability in the construction of lng plant modules has reached an international leading level.